Repairing or maintaining a property sometimes requires access to neighbouring land. Scaffolding may need to be erected in a neighbour’s garden, contractors may need to use an adjoining passageway, or a wall may only be accessible from the other side of the boundary.
In many cases, suitable arrangements can be agreed between the owners. If consent is refused, the Access to Neighbouring Land Act 1992 may allow an owner to apply to the County Court for an order granting temporary access.
The Act does not provide a general right to enter neighbouring land. Entering without the neighbour’s consent or a court order may amount to trespass.
When an access order may be made
The court may make an access order where entry onto neighbouring land is reasonably necessary to carry out works for the preservation of the applicant’s land. The applicant must also show that the work would be impossible, or substantially more difficult, without access.
Preservation work may include maintaining, repairing or renewing a building. It can also include work to drains, sewers, pipes and cables, as well as certain work involving hedges, trees, shrubs and ditches.
Access must be reasonably necessary rather than merely convenient. The fact that using the neighbour’s land would make the work cheaper or easier may not, by itself, be enough.
Improvements and alterations
The Act is mainly concerned with maintaining and repairing existing property. It does not give an owner an unrestricted right to enter neighbouring land to build an extension or carry out development.
An access order may sometimes include an alteration, adjustment or improvement where it is reasonably necessary for the full and effective preservation of the property. The court will consider the benefit of the proposed work and whether including it would cause substantial hardship to the neighbour.
A project that is purely an improvement, without a genuine preservation purpose, is less likely to fall within the Act.
Asking a neighbour for access
Court proceedings should usually be a last resort. The owner seeking access should first explain what work is proposed, why access is needed and how long it is likely to take.
The request should also address practical matters such as working hours, scaffolding, insurance, security and the steps that will be taken to protect the neighbouring property. Plans, photographs and a contractor’s method statement may help the neighbour understand the proposal.
If agreement is reached, it should be recorded in writing. For substantial or lengthy work, a formal access licence may be appropriate. This can specify the permitted work, dates and times of entry, insurance requirements and responsibility for any damage.
What the court will consider
An access order is not automatic. The court will consider the need for the work and the effect that entry would have on the adjoining owner or occupier.
An order may be refused if access would cause an unreasonable degree of interference with the use or enjoyment of the neighbouring land. The court will also consider whether the order would cause hardship to an affected person.
The extent and duration of the proposed access will be relevant. So will the likely noise, dust, loss of privacy, security concerns and risk of damage. The availability of another practical way to carry out the work may also be important.
The applicant should therefore seek no more access than is reasonably necessary and should propose suitable measures to minimise disruption.
Terms of an access order
An access order can define the area that may be entered, the work that may be carried out and the people authorised to enter. It may also specify the dates, times and duration of access.
The court can impose conditions dealing with scaffolding, equipment, insurance, security, cleaning and reinstatement. The order may require notice to be given before entry and may provide for compensation or other payments.
The applicant and contractors must remain within the terms of the order. It does not authorise additional work or continued access after the permitted period has ended.
Compensation and damage
The court may require the applicant to compensate the neighbour for loss, damage or injury caused by the authorised entry and work. In some cases, a payment may also be ordered for the privilege of entering the neighbouring land.
The amount and type of payment will depend on the proposed work and its effect on the neighbour. Evidence may be required concerning disruption, loss of use or the cost of repairing damage.
It is often sensible to prepare a photographic schedule of condition before work begins. This records the condition of the neighbouring property and may reduce the scope for disagreement afterwards.
Entering without permission
An owner should not assume that the need to carry out repairs creates an immediate right of entry. Entering without permission or an access order may amount to trespass.
The neighbour may seek an injunction to prevent further access and may claim damages for any loss caused. Necessary work can therefore be delayed if the correct arrangements are not made before contractors attend.
Urgency may justify dealing with an application quickly, but it does not create a general right to enter another person’s land.
Responding to a request for access
A neighbour who receives a request for access does not have to accept unclear or unnecessarily wide proposals. Further information can be requested about the work, the contractor, insurance arrangements and the precautions that will be taken.
Reasonable concerns about privacy, security, timing and potential damage should be raised at an early stage. It may be possible to address them through conditions in an access licence.
An outright refusal may lead to a court application. The parties’ conduct, including whether they made reasonable attempts to reach agreement, may later be relevant when the court considers costs.
Boundary and party wall issues
An access order will not usually decide the legal boundary between the properties. If ownership of the land is disputed, that issue may need to be considered separately.
The Access to Neighbouring Land Act 1992 is also distinct from the Party Wall etc. Act 1996. The Party Wall etc. Act applies to certain work involving shared structures, construction at the boundary and excavation near neighbouring buildings.
A property owner may need to comply with the Party Wall etc. Act even if access has been agreed or ordered. Equally, following the party wall procedure may not resolve every issue concerning access to the neighbour’s land.
Costs and proportionality
Court proceedings may involve legal costs, expert evidence and delay. Even where access is granted, the applicant may have to pay compensation and comply with detailed conditions.
The parties should therefore consider whether the dispute can be resolved through a carefully drafted access licence. Clear information about the work and sensible protections for the neighbouring property will often make agreement more likely.
Where agreement is not possible, the proposed access should be defined precisely and supported by evidence explaining why it is reasonably necessary.